Earned-Value Analysis. A Project Budget Calls For The Following Expenditures:

 

Define each term in your own words, calculate these values for the above project, and show your work:

  1. Budgeted cost baseline (make a graph illustrating this one)
  2. Budget at completion (BAC)
  3. Planned value (PV) as of May 1
  4. Earned value (EV) as of May 1 if the foundation work is only two-thirds complete. Everything else is on schedule.
  5. SV as of May 1.
  6. Actual cost as of May 1 is $160,000. Calculate the cost variance (CV) as of May 1.
  7. Schedule performance index (SPI)
  8. Cost performance index (CPI)
  9. Estimate to complete (ETC), assuming that the previous cost variances will not affect future costs
  10. Estimate at completion (EAC)

The post Earned-Value Analysis. A Project Budget Calls For The Following Expenditures: appeared first on essaypages.

We offer homework writing services with you in mind. Our homework help service is made to meet your demands, whatever the challenge. Every paper is written from scratch by experts in your field. You can order essays, discussion, article critique, coursework, projects, case study, term papers, research papers, reaction paper, movie review, research proposal, capstone project, speech/presentation, book report/review, annotated bibliography, and more.

Your Writing Help Service in a Nutshell

PLACE YOUR ORDER